A release every four to six weeks
- RefinementSpecs shaped with developers and QA
- Sprint 1Build, demo review, test
- Sprint 2Build, demo review, test
- Mop-up weekCatch-up before release
- ReleaseRelease notes out
Each release is two sprints plus a mop-up week. I plan two delivery streams side by side, with team labels in Jira so each stream’s work stays visible on its own.
Nothing starts without these five
- A clear expected end result
- Acceptance criteria
- What’s out of scope
- QA scenarios
- No open product questions
Done means verified, not just merged
- The ticket matches what was built
- Any investigation is linked
- Code reviewed and merged
- I’ve verified it on staging myself before it closes
For anything complex, I run an investigation first, with its own expected outputs and acceptance criteria. Once it’s done, the build gets planned ticket by ticket.
Investigations had no proper route to Done in our Jira, so I took leadership to a decision to add a dedicated Spike ticket type with its own workflow: In Progress, PO review, Done.
I built a live sprint tracker from Jira that shows each developer’s load before we commit to a sprint.
It has flagged an over-capacity sprint and a dependency conflict before planning, and caught a double-counted estimate. I also plan around Finnish public holidays for colleagues in Finland.
My developers and QA are spread across the UK, Finland and India, with a shared working window of four to five hours. I wrote a meeting plan across the three time zones and developers work one ticket at a time.
On big programmes I split the backlog into three trackers: the MVP, customer-specific needs and nice-to-haves. With a fixed customer deadline I’ve traded scope, dropping date-based comparison so a customer’s tables came sooner. I’ve also held a feature back a release so QA could clear every issue first.